Taurus — Temmuz 2026

2026-06-27 — 2026-07-31 · Jira + Timepiece (n8n canli) · ← tum takimlar
Takim Success
%67.6
Takim Due Date
%100
Toplam Target
526.5 efor
Toplam Realization
356 efor
Dev / QA
2 / 2
Escape (QR/UAT)
1 / 1
Takim — Gecen Aya Gore
Takim hedefin altinda kaldi (%67.6). Dikkat: success %105.6'den %67.6'e geriledi; escape artti (0→2).
Takim Success
▼%38
onceki%105.6
bu ay%67.6
Toplam Realization
▼18.5 efor
onceki374.5 efor
bu ay356 efor
Due Date
▲%2.1
onceki%97.9
bu ay%100
Toplam Task
▼4
onceki101
bu ay97
CR+QA Fix
▲7
onceki4
bu ay11
QR+UAT Escape
▲2
onceki0
bu ay2
Anıl NuhoğluDeveloper
Board Task
31
Target
115
Realize
116
Success
100.9%
Due Date Acc
100%
CR / QA Fix
1 / 6
PerformansHedef karsilandi (%100.9).
Kod Kalitesi7 CR+QA fix / 31 task — makul seviye.
TerminDue date dogrulugu %100 (27/27).
Ek Sorumluluk3 urgent, 8 meeting, 8 web service task ustlendi — ekstra katki (pozitif).
Excluded4 task rejected — metriklere dahil degil.
Gecen Aya Goresuccess ▼22% (122.9→100.9%); efor ▲11.5 (104.5→116).
Gelistirilmesi Onerilenbu ay belirgin gelisim alani yok — tum KPI'lar hedefte.
Talha ErbirDeveloper
Board Task
17
Target
121
Realize
105.5
Success
87.2%
Due Date Acc
100%
CR / QA Fix
1 / 3
PerformansHedefin altinda (%87.2, min %85).
Web ServiceHic WS taski yok — WS almali.
UrgentHic urgent task yok (takim ort. 0.8) — urgent almali.
Kod Kalitesi4 CR+QA fix / 17 task — makul seviye.
TerminDue date dogrulugu %100 (13/13).
Ek Sorumluluk2 meeting task ustlendi — ekstra katki (pozitif).
Excluded1 task rejected — metriklere dahil degil.
Gecen Aya Goresuccess ▼12.8% (100→87.2%); efor ▲28.5 (77→105.5).
Gelistirilmesi Onerilenbu ay belirgin gelisim alani yok — tum KPI'lar hedefte.
Mustafa ALTUNQA
QA Task (QA-type)
27
Board Task (DEV-type)
15
Target
128
Realize
126
Success
98.4%
QR Fix
0
UAT Fix
1
PerformansHedefin altinda (%98.4, min %85).
UrgentHic urgent task yok (takim ort. 0.8) — urgent almali.
QR Escape0 QR fix (%0, hedef ≤%7.5).
UAT Escape1 UAT fix (%2.33, hedef ≤%5).
TerminDue date dogrulugu %100 (43/43).
Ek Sorumluluk1 meeting, 2 web service task ustlendi — ekstra katki (pozitif).
Gecen Aya Goresuccess ▼4% (102.4→98.4%); efor ▲42 (84→126).
Gelistirilmesi Onerilenbu ay belirgin gelisim alani yok — tum KPI'lar hedefte.
Asena KarakaşQA
QA Task (QA-type)
1
Board Task (DEV-type)
5
Target
162.5
Realize
8.5
Success
5.2%
QR Fix
1
UAT Fix
0
PerformansHedefin belirgin altinda (%5.2).
MeetBu ay hic Meeting taski yok — meetlere katilmali.
UrgentHic urgent task yok (takim ort. 0.8) — urgent almali.
QR Escape1 QR fix (%16.67, hedef ≤%7.5).
UAT Escape0 UAT fix (%0, hedef ≤%5).
TerminDue date dogrulugu %100 (6/6).
Ek Sorumluluk1 alert task ustlendi — ekstra katki (pozitif).
Gecen Aya Goresuccess ▼93.4% (98.6→5.2%); efor ▼100.5 (109→8.5).
Gelistirilmesi Onerilenefor hedegine ulasilamadi (%5.2) — planlama/WIP gozden gecirilmeli
Gelistirilmesi OnerilenQR kacagi hedef ustu — QA checklist derinlestirilmeli
Realization tanimi Insight ile birebir (UAT Date penceresi + kanonik status seti, OPT+VLS+SRTR). Timepiece sureleri lead-times sheet'lerinden. Rejected task'lar metrik disi.