Hydra — Temmuz 2026 · Kisi Bazli Detayli Performans Analizi

Sprint: 2026-06-27 — 2026-07-24  ·  3 Developer, 2 QA
Kaynak: Jira (OPT board) · uretim 2026-07-29 · 166 task tarandi

Executive Summary

81.5%
Takim Success
96.7%
Takim Due Date Acc
718 efor
Toplam Target
585.5 efor
Toplam Realization
3 / 2
Dev / QA
1 / 1
Escape (QR / UAT)

Haziran → Bu Ay — Kisi Bazli Success Degisimi

KisiRolHaziranBu AyDegisim (pp)
Bulutay SaraçDev100%91.9%▼ 8.1
Baran ArslanDev79.3%74.4%▼ 4.9
Yarkın SöylerDev104.5%68.4%▼ 36.1
Başak YılmazQA107.3%86.8%▼ 20.5
Abdüssamed ÖzacarQA107.7%85.2%▼ 22.5

Karsilastirma Grafikleri

Success Rate (%) — Tum Ekip

Due Date Accuracy (%)

Fix Dagilimi (CR / QA / QR / UAT)

Task Sayisi & Effort Average

Kisi Bazli Detayli Analiz — Developers

Bulutay SaraçDeveloper
26
Board Task
136
Target
124
Realize
91.9%
Success
100%
Due Date Acc
1 / 3
CR / QA Fix
Success: %91.9 — hedefe yakin, 11 efor eksik.
Kod Kalitesi: temiz — 1 CR + 3 QA fix / 26 task (task basi 0.15).
Termin: tum task'lar due date'inde teslim.
Ek Sorumluluk: 2 urgent, 2 meeting, 6 web service task ustlendi — ekstra katki/yuk (pozitif).
Excluded: 4 task rejected — metriklere dahil degil.
Gecen Aya Gore: success ▼8.1% (100→91.9%); efor ▲28 (97→125); fix ▲2 (2→4).
Gelistirilmesi Onerilen: bu ay belirgin bir gelisim alani yok — tum KPI'lar hedefte. Mevcut tempo korunmali.
Genel Degerlendirme: Guclu yonler: temiz kod, 10 ek-sorumluluk.
Board task detayi (30)
TaskTakimEforCR/QA FixDurum
OPT-233993Hydra270/0Done
OPT-234824Hydra211/0Done
OPT-236884Phoenix130/0Done
OPT-237246Hydra80/0Done
OPT-235972Hydra80/0Done
OPT-237465Hydra50/0Done
OPT-237283Hydra50/0Done
OPT-236897Hydra30/0Done
OPT-236773Hydra30/0Done
OPT-23667530/0Done
OPT-236665Hydra30/0Done
OPT-236506Hydra30/0Done
OPT-236405Hydra30/0Done
OPT-235014Hydra30/0Done
OPT-237432Hydra20/0Blocked (Partner)
OPT-237106Hydra20/0Blocked (Partner)
OPT-237068Hydra20/0Rejected
OPT-236935Hydra20/0Done
OPT-236746Hydra20/0Done
OPT-236349Hydra20/0Done
OPT-235982Hydra20/0Rejected
OPT-235870Hydra20/0Done
OPT-235814Hydra20/0Rejected
OPT-235602Hydra20/0Done
OPT-235521Hydra20/0Done
OPT-234932Hydra20/0Done
OPT-233788Hydra20/0Done
OPT-236591Hydra10/0Rejected
SRTR-32112Hydra00/3UAT PARTNER
SRTR-32011Scorpius00/0Blocked (CSM)
Baran ArslanDeveloper
35
Board Task
142.5
Target
106
Realize
74.4%
Success
100%
Due Date Acc
6 / 19
CR / QA Fix
Success: %74.4 — hedefin altinda; 36.5 efor teslim edilemedi (106/142.5).
Kod Kalitesi: yuksek donus — 6 CR + 19 QA fix / 35 task (task basi 0.71); grooming/self-review guclendirilebilir.
Termin: tum task'lar due date'inde teslim.
Excluded: 3 task rejected — metriklere dahil degil.
Gecen Aya Gore: success ▼4.9% (79.3→74.4%); efor ▲37 (69→106); fix ▲16 (9→25).
Gelistirilmesi Onerilen: efor hedefine ulasilamadi (%74.4, 36.5 efor acik) — task tahmini/planlama ve WIP yonetimi gozden gecirilmeli
Gelistirilmesi Onerilen: kod donusu yuksek (25 CR+QA fix / 35 task = task basi 0.71) — grooming, self-review ve PR oncesi kontrol guclendirilmeli
Genel Degerlendirme: Odaklanilacak: hedef alti (%74.4).
Board task detayi (38)
TaskTakimEforCR/QA FixDurum
OPT-236161Hydra131/1Done
OPT-237012Hydra81/1UAT PARTNER
OPT-234928Hydra81/3Done
OPT-234671Hydra80/1Done
OPT-236310Hydra50/1Done
OPT-233367Hydra50/2Done
SRTR-31951Aquila30/1Done
OPT-237362Hydra30/0UAT PARTNER
OPT-237260Hydra31/0Blocked (Partner)
OPT-237069Hydra30/0UAT PARTNER
OPT-236810Hydra30/0Done
OPT-236805Hydra30/0Done
OPT-23652530/0Done
OPT-235924Hydra30/1Done
OPT-235790Hydra31/1Done
OPT-235445Hydra30/1Done
OPT-23537730/0Done
OPT-235198Hydra30/0Blocked (Partner)
OPT-237015Hydra20/1UAT REPORTER
OPT-236959Hydra20/0Done
OPT-236958Hydra20/0Rejected
OPT-236957Hydra20/0Done
OPT-236947Hydra20/2Done
OPT-236703Hydra20/0Done
OPT-236556Hydra21/0Done
OPT-236359Hydra20/0Done
OPT-236308Hydra20/1Done
OPT-236249Hydra20/0Done
OPT-236207Hydra20/0Done
OPT-235849Hydra20/0Done
OPT-235792Hydra20/0Done
OPT-235710Hydra20/0Done
OPT-235451Hydra22/0Rejected
OPT-235269Hydra20/0Done
OPT-237202Hydra10/0Blocked (CSM)
OPT-236624Hydra10/2Done
SRTR-32132Andromeda00/0UAT REPORTER
SRTR-31993Scorpius00/0Rejected
Yarkın SöylerDeveloper
21
Board Task
133
Target
91
Realize
68.4%
Success
94.74%
Due Date Acc
2 / 6
CR / QA Fix
Success: %68.4 — hedefin altinda; 42 efor teslim edilemedi (91/133).
Kod Kalitesi: orta — 2 CR + 6 QA fix / 21 task (task basi 0.38).
Ek Sorumluluk: 1 meeting, 1 web service task ustlendi — ekstra katki/yuk (pozitif).
Excluded: 2 task rejected — metriklere dahil degil.
Gecen Aya Gore: success ▼36.1% (104.5→68.4%); efor ▲45 (46→91); fix ▼1 (9→8).
Gelistirilmesi Onerilen: efor hedefine ulasilamadi (%68.4, 42 efor acik) — task tahmini/planlama ve WIP yonetimi gozden gecirilmeli
Genel Degerlendirme: Odaklanilacak: hedef alti (%68.4), gecen aya gore belirgin dusus.
Board task detayi (23)
TaskTakimEforCR/QA FixDurum
OPT-235926Hydra340/0Blocked (Partner)
OPT-235770210/0Done
OPT-235953170/0Done
OPT-234894Hydra131/1Done
OPT-236730Hydra50/0Development InProg
OPT-235772Hydra50/0Done
OPT-237135Hydra30/0Rejected
OPT-237058Hydra30/0Done
OPT-236414Hydra30/1Done
OPT-235965Hydra30/0Done
OPT-235871Hydra30/0Done
OPT-235434Hydra30/0Done
OPT-235019Hydra30/0Done
OPT-237116Hydra20/0UAT PARTNER
OPT-236832Hydra20/0Done
OPT-236698Hydra20/0Done
OPT-236583Hydra20/0Done
OPT-235973Hydra20/0Done
OPT-235612Hydra20/0Rejected
OPT-234885Hydra20/0Done
OPT-234880Hydra20/0Done
OPT-234740Hydra20/0Done
OPT-236894Hydra11/4Done

Kisi Bazli Detayli Analiz — Quality Assurance

Abdüssamed ÖzacarQA
14
QA Task (QA-type)
26
Board Task (DEV-type)
162.5
Target
138.5
Realize
85.2%
Success
1
QR Fix
1
UAT Fix
QR Fix: 1 fix / 45 task = %2.2 — resmi hedefin (≤%7.5) ALTINDA, iyi.
Success: %85.2 — hedefe yakin, 24 efor eksik.
UAT Escape: 1 fix / 45 task = %2.2 — QA'dan gecip musteride cikan defect (resmi hedef ≤%5, max %15).
Is Yuku: 40 task test edildi: 26 board (DEV-type) + 14 QA-type.
Ek Sorumluluk: 1 urgent, 3 web service, 3 alert task ustlendi — ekstra katki/yuk (pozitif).
Gecen Aya Gore: success ▼22.5% (107.7→85.2%); efor ▲12.5 (126→138.5); fix sabit (2).
Gelistirilmesi Onerilen: bu ay belirgin bir gelisim alani yok — tum KPI'lar hedefte. Mevcut tempo korunmali.
Genel Degerlendirme: Guclu yonler: 7 ek-sorumluluk. Odaklanilacak: 1 QR kacagi, 1 UAT escape, gecen aya gore belirgin dusus.
QA task detayi (48)
TaskTakimQA EforQR/UAT FixDurum
OPT-236467Hydra280/0Done
OPT-237616Hydra15.50/0Done
OPT-237012Hydra80/0UAT PARTNER
OPT-235961Andromeda80/0Done
OPT-234671Hydra50/0Done
OPT-233993Hydra50/0Done
OPT-237213Hydra30/0Done
OPT-236990Orion30/0UAT PARTNER
OPT-236698Hydra30/0Done
OPT-236583Hydra30/0Done
OPT-236358Hydra30/0Rejected
OPT-236177Taurus30/0Done
OPT-235999Hydra30/0Done
OPT-235792Hydra30/0Done
OPT-235612Hydra30/0Rejected
OPT-235300Hydra30/0Done
SRTR-32162Hydra20/0Done
OPT-237245Hydra20/0UAT REPORTER
OPT-237140Hydra20/0UAT InProg
OPT-237015Hydra20/0UAT REPORTER
OPT-236775Hydra20/0Done
OPT-236700Perseus20/0Done
OPT-236626Volans20/0Done
OPT-236532Taurus20/0Done
OPT-236336Hydra20/0Done
OPT-236308Hydra20/0Done
OPT-236178Andromeda20/0Done
OPT-236000Hydra20/0Done
OPT-235772Hydra20/0Done
OPT-235704Hydra20/0Done
OPT-23528720/0Done
OPT-234880Hydra20/1Done
SRTR-32100Cygnus10/0Blocked (Partner)
SRTR-32099Hydra10/0Done
SRTR-32084Hydra10/0Done
SRTR-32077Hydra10/0Done
SRTR-32044Hydra10/0Done
SRTR-31975Hydra10/0Backlog.
OPT-237382Hydra10/0Blocked (CSM)
OPT-236959Hydra10/0Done
OPT-236677Hydra10/0Done
OPT-235980Taurus10/0Done
OPT-235965Hydra10/0Done
OPT-235177Hydra10/0Rejected
OPT-234885Hydra11/0Done
OPT-237537Hydra0.50/0UAT REPORTER
OPT-237413Hydra0.50/0Blocked (OXT)
OPT-231011Volans00/0Blocked (CSM)
Başak YılmazQA
10
QA Task (QA-type)
27
Board Task (DEV-type)
144
Target
125
Realize
86.8%
Success
0
QR Fix
0
UAT Fix
QR Fix: 0 — QR'da kacan defect yok (42 task). Resmi hedef ≤%7.5.
Success: %86.8 — hedefe yakin, 19 efor eksik.
Is Yuku: 37 task test edildi: 27 board (DEV-type) + 10 QA-type.
Ek Sorumluluk: 1 urgent, 4 web service, 5 alert task ustlendi — ekstra katki/yuk (pozitif).
Gecen Aya Gore: success ▼20.5% (107.3→86.8%); efor ▼8 (133→125); fix sabit (0).
Gelistirilmesi Onerilen: bu ay belirgin bir gelisim alani yok — tum KPI'lar hedefte. Mevcut tempo korunmali.
Genel Degerlendirme: Guclu yonler: QR kacagi yok, 10 ek-sorumluluk. Odaklanilacak: gecen aya gore belirgin dusus.
QA task detayi (42)
TaskTakimQA EforQR/UAT FixDurum
OPT-236445Hydra26.50/0Done
OPT-237687Hydra13.50/0Done
OPT-237008Perseus80/0Done
OPT-236768Taurus50/0UAT PARTNER
OPT-236005Hydra50/0Done
OPT-233997Aquila50/0Done
OPT-236937Pegasus30/0Blocked (Partner)
OPT-235586Hydra30/0Done
OPT-235521Hydra30/0Done
OPT-235445Hydra30/0Done
OPT-235183Cygnus30/0Done
OPT-233367Hydra30/0Done
SRTR-32020Hydra20/0Done
OPT-237510Hydra20/0UAT REPORTER
OPT-237031Hydra20/0Done
OPT-236999Perseus20/0Done
OPT-236935Hydra20/0Done
OPT-236914Volans20/0UAT REPORTER
OPT-236876Aquila20/0Done
OPT-236805Hydra20/0Done
OPT-236034Hydra20/0Blocked (OXT)
OPT-235924Hydra20/0Done
OPT-235402Taurus20/0Done
OPT-235293Volans20/0Done
OPT-235041Pegasus20/0Done
OPT-235024Andromeda20/0Done
OPT-230879Volans20/0Done
OPT-237313Hydra1.50/0Blocked (OXT)
SRTR-32079Hydra10/0Done
SRTR-32071Scorpius10/0Done
SRTR-32009Hydra10/0Done
SRTR-31931Hydra10/0Done
SRTR-31549Hydra10/0Done
OPT-237106Hydra10/0Blocked (Partner)
OPT-235983Taurus10/0Done
OPT-235973Hydra10/0Done
OPT-235904Hydra10/0Done
OPT-235901Hydra10/0Done
OPT-235575Hydra10/0Done
OPT-235471Hydra10/0Done
OPT-235685Hydra0.50/0Done
OPT-237342Pegasus00/0UAT InProg

Fix Analizi — Code Quality & Test Kalitesi

KisiRolCR FixQA FixQR FixUAT FixFix/Task
Bulutay SaraçDev1315.4%
Baran ArslanDev61971.4%
Yarkın SöylerDev2638.1%
Abdüssamed ÖzacarQA11
Başak YılmazQA00

Genel Siralama — Tum Ekip (Dev: Board Success · QA: QA Success)

#KisiRolSuccessDue AccFix/TaskDegerlendirme
1Bulutay SaraçDev91.9%100%15%Cok Iyi
2Baran ArslanDev74.4%100%71%Gelisime Acik
3Yarkın SöylerDev68.4%94.74%38%Gelisime Acik
4Başak YılmazQA86.8%97.3%0%Iyi
5Abdüssamed ÖzacarQA85.2%92.5%4%Iyi

Key Takeaways & Aksiyon Onerileri

En dusuk success: Yarkın Söyler (%68.4) — destek gerekebilir.
QR fix alan QA'lar: Abdüssamed Özacar — QA cikislari gozden gecirilmeli.
En temiz kod: Bulutay Saraç — en dusuk fix orani.
Takim board success %81.5, due date accuracy %96.7.
Takim Success = toplam realization / toplam target (rejected task'lar HARIC). Efor Basi Saat = InProg suresi / SP. Saat = InProg status suresi (wall-clock, net mesai degil). Fix count'lari Insight ile birebir tutar. Rol: Developer alani (cf_13202)→Dev, QA Tester (cf_13401)→QA. Jira-native — Insight klonu degil.